Fuselage:  August 18, 2007 - Present
Home     Empennage    Wing Kit    Fuselage Kit    Finish Kit    
Avionics    Firewall Forward   Final Stages  
8/14/07   It's here!!!!!  Going to begin inventorying tomorrow.











8/18/07  Completed the firewall this weekend. Stainless steel is a pain in the butt to drill!











8/25/07   Complete the center section bulk head today. Also did the initial fit up and installation of the control stick        
               system.












10/16/07  I really haven't had much time to update everything lately, as you can see from the gap in log entries. Since  
                my last log entry, I have completed all of the bulkhead prep and have began the initial construction phase of
                the aft fuselage section. The aft section has been fitted, leveled and is now ready to begin drilling the           
                stiffeners to the lower skins. Thanks to Greg Vouga, the longerons are correctly bent and ready for               
                installation. Greg and I spent an afternoon bending the longerons in his hanger. Greg's 7A is nearing the     
                final building stages with the engine and baffles in place, and instruments nearly installed. Below are photos
                of the aft fuselage section resting upside down and level in preparation for match drilling the side stiffeners.











12/25/07  Sorry for the long delay updating my site!  Haven't had much time to work on the plane until recently. But...   
                since I have gotten back to work on it, with some help from my son Brandon, I was able to rivet the bottom     
                skin  on the center section and  do the initial installation of the front and middle sections of the fuselage.       
                The longerons matched the curvature of the air frame perfectly! Didn't need to adjust them at all to make      
                them line up with the pre-punched holes on the side skins. The longerons have both been match drilled        
                and I am now ready for the initial installation the firewall and forward bottom skin. Both stabilizers are just      
                resting in position for show : )











12/29/07  Firewall and bottom skin installation went like a charm. Didn't need any trimming of the longerons at all. I am
                now preparing the lower longerons for installation They both require a lot of twisting and notching in order    
                to fit properly.












1/6/08    Did the initial installation of the forward fuselage this weekend. Fitted the rudder and brake pedals along with  
              some optional adjustment holes in case someone needs to adjust the length of the pedals in the future.          
              Installed all the floor stiffeners and bottom skin. It's almost ready to take apart and prep for riveting.

1/20/08  Well... I hated to do it, but I took it all apart and began the tedious task of cleaning up all the parts, deburring  
              them and making all the final preparations prior to riveting them together for the last time. Took out the           
              longerons, deburred them and did the required countersinking. Lots more to do....

3/10/08  Sorry for the long delay updating the site!  Over the past month or so I have nearly completed riveting on the
              side skins and installed a hoist in the shop enabeling me to raise and lower the fuselage to a good working     
              height, also making it easy to spin the fuselage on it's center axis allowing me easy access to the inside of      
              the fuselage without crawling around inside of it!  Riveted on the aft deck so the fuselage is completely rigid    
              now with no flex at all. I am nearly at the "quick build" stage... after 2 years, and looking forward to the next 2  
              years or so before completion... at least that's the plan...  : )











7/20/08  Well... in the beginning it was fun updating the website.  Maybe because every time I made some progress it   
              was noticeable!  As most of the airframe is completed, at the progress is barely noticeable at all. I have spent
              the weekends over the last 4 months running conduit through the back of the airframe, preparing all of the     
              baggage compartment panels for final installation, both front and rear floorboards are ready for final               
              installation and I just completed both seat backs this afternoon. I have been holding off riveting the                  
              floorboards and baggage compartment floors on permanently until I get all of my wiring run through the tail     
              section. There are a few components that I will need wiring access back there. I am going to install a rear        
              strobe light in the bottom of the rudder, I have already installed an electric trim tab servo that will need wiring  
              run to it, I am planning to install the ELT behind the baggage compartment and an auto pilot servo that will      
              need to be mounted in the tail as well.  The photo on the r
ight above is of the nearly completed passenger     
              
and baggage compartments. The photo on the right is how I have the airframe supported by an electric hoist  
              
in the ceiling making it EASY to work on the floors and side panels without having to even bend over. What a  
              time and BACK saver!  
I also use the hoist as a space saver! (Left below)  Well.... that's all for now. I will be     
              
leaving for OSHKOSH next week and staying there for a week.  Hope to see you there!











9/7/08  Oshkosh was GREAT!  What a motivator to get this bird in the air!  Well, the last few weekends have been        
            extremely productive. The wings are on for the 1st time, I have run all of my fuel lines and vent lines, installed   
            the rudder pedals with the master cylinders for the dual brake system, attached the empennage                        
            PERMANENTLY, installed the elevators and rudders so all of the control surfaces are now functioning properly
            from inside the cabin. It looks like I am running out of things to do before my finish kit comes so I will probably    
            begin the nasty job of finishing the control surface tips with fibreglass. I will also be installing the wing tip            
            landing lights and nav lights as well as running the required wiring.  I really need to get my panel laid out so I    
            can begin working on the front top skins preparing for the tip up canopy installation.
My daughter
Kristin can't wait
to get this bird
in the air either!
She was only 1
year old when I
began this
project! Now
she's 4!